Team Oriano exhibited commitment towards Customer, Investor and Vendors
Mumbai-headquartered Oriano Clean Energy has commissioned 26 MWac/36 MWp Solar Park at 110 kV at Raichur in Karnataka under Group Captive Open Access Mechanism for one of the Global Pharma power off-taker.
Oriano was awarded for the Project with scope of Captive PPA/SHA acquisition, Third Party Legal Land due diligence and 100+ Acres Land acquisition, All Land and Development as well as Project related approvals including Solar Park. The turnkey EPC project work included construction of 110 kV switchyard and 110 kV transmission line.
It’s an end-to-end Project offered by Oriano including 5 years of O&M.
Team Oriano exhibited their commitment towards their Customer, Investor and Vendors despite Covid, multiple lockdowns across the country, development related challenges, material uncertainty in terms of supply and commercial escalations. Oriano commissioned the project in a timely manner with all compliances.
Lokendra Singh, Oriano Director & Co-Founder, said, “As a strategy to extend beyond Utility scale turnkey Solar Project EPC, it’s the first project delivered by Oriano on Turnkey Development and EPC mode under Group Captive Open Access Mechanism. The challenges and timelines were daunting due to Covid restrictions and heavy rains among others.”
The project site construction started in mid of July 2021 and took 4 months to fully commission and charge the Project with 110 kV Bay, TL and GSS Infrastructure, he said in a release on 15 Nov 2021.
Oriano is developing four additional Solar parks in multiple states of 100 MWp (Maharashtra), 125 MWp (Karnataka), 50 MWp (Tamil Nadu) and 70 MWp (Chhattisgarh) and are in advance stages. Oriano is additionally working on Wind Solar Hybrid Project in Karnataka.
Oriano is additionally currently constructing approx. 150+ MWp multiple projects in Chhattisgarh on Captive Open Access Mechanism at 132 kV Evacuation. #project #renewables #solar /fiinews.com